Articles/How Long Does a 30-Year Inspection Take?

How Long Does a 30-Year Building Inspection Take in Miami?

From the day you receive the county notice to the day you get approval — here is the complete timeline for Miami-Dade and Broward 30-year recertifications, with the exact factors that speed it up or slow it down.

The Short Answer

For most buildings in Miami-Dade and Broward, the full 30-year recertification process takes 6–12 weeks from the first site visit to county approval. The site visit itself is just one day. Most of the time is in report preparation (1–3 weeks) and county review (2–6 weeks). If repairs are required, add 4–16 weeks on top.

The Complete 30-Year Inspection Timeline

Phase 1

Notice & Engineer Selection

1–2 weeks
  • Receive county recertification notice
  • Contact and vet licensed structural engineers
  • Get quotes and select your engineer
  • Sign contract and schedule site access
Phase 2

Site Inspection

1 day (2–6 hours)
  • Structural inspection of all common areas
  • Balconies, columns, slabs, and roof
  • Parking structure and foundation
  • Electrical panel and wiring inspection
Phase 3

Report Preparation

1–3 weeks
  • Engineer reviews inspection findings
  • Photo documentation compiled
  • Deficiency descriptions and recommendations written
  • PE stamps and signs final report
Phase 4

County Submittal & Review

2–6 weeks
  • Report submitted to Miami-Dade or Broward
  • County reviews for completeness
  • Any requested revisions addressed
  • Final approval issued

Total Timeline Summary

Best case (no issues)

5–7 weeks

Small building, no deficiencies, fast county review

Typical case

8–12 weeks

Average-sized building, minor deficiencies, standard review

Complex case

16–24 weeks

Phase 2 required, repairs needed, or county revision requests

5 Factors That Slow Down Your Recertification

Building access issues

Add 1–2 weeks

Schedule inspection access across all units and areas at the time of contract signing.

Phase 2 testing required

Add 2–4 weeks

If deficiencies are found during Phase 1, Phase 2 destructive testing extends the total timeline significantly.

Incomplete building records

Add 1–2 weeks

Having prior inspection reports, repair records, and original construction documents ready speeds up the engineer review.

Repair work required before approval

Add 4–16 weeks

If the county requires repairs before final approval, the clock runs on contractor availability and permit pull time.

County review backlog

Add 2–4 weeks

Spring and post-storm seasons create review backlogs. Submit early to avoid being caught in the queue.

You Have 90 Days From the County Notice

Miami-Dade gives you 90 calendar days from the date of notice to submit the completed recertification report. Given that the full process typically takes 6–12 weeks, there is almost no margin if you wait before hiring an engineer.

If you have already received a notice, contact us immediately. We can tell you exactly how much time you have and whether an expedited process is needed.

Related Services

Frequently Asked Questions

How long does the 30-year inspection site visit take?

The actual site visit takes 2–6 hours for most buildings. Larger buildings (100+ units, multiple towers) may require a second visit or a full day. The site visit is only a fraction of the total timeline — report preparation and county review take the most time.

How long does Miami-Dade take to approve a recertification report?

Miami-Dade Building Department typically takes 2–6 weeks to review and approve a submitted recertification report. During peak season (spring) it can take longer. We track all submissions and follow up proactively to avoid delays.

Can the 30-year inspection be expedited?

Yes. We offer expedited 2–3 week turnaround for the inspection and report when buildings are approaching their 90-day deadline. Miami-Dade also offers expedited review for an additional fee.

What happens if we miss the 90-day deadline?

Miami-Dade can issue daily fines of up to $1,000 per day and in extreme cases issue an unsafe occupancy order. If you have received a notice, contact us immediately — we can usually complete the inspection and report well within the 90-day window.

Does Phase 2 testing extend the timeline?

Yes. If Phase 2 destructive testing is required, add 2–4 additional weeks to the timeline. This allows time to open test areas, complete laboratory analysis, and prepare the supplemental Phase 2 report.